Project Execution
TOTAL POINTS 10
1 point
1 point
1 point
![](https://d3c33hcgiwev3.cloudfront.net/imageAssetProxy.v1/dfK8btj0EeWaQgoI1qH58w_7cf630f65ffff31ecb8e02ac736c8c4f_EVA-for-Creative-Task.jpg?expiry=1610668800000&hmac=x66C4PMUFpA-Qf7jfPyvmCjYPpKdUnUpjXNlv6mDpZo)
Use the information in Figure 1 to calculate the Schedule Performance Index (SPI).
1 point
![](https://d3c33hcgiwev3.cloudfront.net/imageAssetProxy.v1/zOw1Ndj0EeWv6g6eMxXZ9Q_6bf0564594f0405b72cff0482d4222b3_EVA-for-Creative-Task.jpg?expiry=1610668800000&hmac=sRT3iXHWe0qzy6xriXy1k5PR_qnnXZ70GXacsn5Kcgc)
Use the information in Figure 1 to calculate the Cost Performance Index (CPI).
1 point
![](https://d3c33hcgiwev3.cloudfront.net/imageAssetProxy.v1/XswccNj1EeWaQgoI1qH58w_30c784c73feba30e16cb47a4745708fe_EVA-for-IT-Task.jpg?expiry=1610668800000&hmac=VG0usCe5--Yyhv08T4TX_K5gJsryoOh4vDmq7fok_bo)
Is this task on schedule?
1 point
![](https://d3c33hcgiwev3.cloudfront.net/imageAssetProxy.v1/lK-8Idj1EeWaQgoI1qH58w_d5b574dc8ea5af6d6792c13a1e76cdd2_EVA-for-IT-Task.jpg?expiry=1610668800000&hmac=awPlAEj0bUIybq3YNAAC2hbuTfQBdN2lU8TRjI7NmB4)
Is this task on track to be within its budget?
1 point
1 point
1 point
1 point